Thursday, June 9th, 2011

The solar panels are now on the roof on the south side. The walls in the Stables have been plastered and have had the first coat of paint– it is almost looking habitable. We just need some stairs!

We are well ahead of schedule and hope to be open by December.

Solar panels on south side of barnUpstairs of the stables cottage

April 2011

Thursday, June 9th, 2011

The topping out ceremony on the roof – 21st April – the last ridge tile was laid by Andrew.

Under floor central heating has been installed in the Stables and the Cart Shed. The oak windows are all fitted now making the barns watertight!

Underfloor heating being addedTopping out ceremony

March 2011

Thursday, June 9th, 2011

The roofers have been working hard for more than a month, insulating and tiling the roof – 10,000 slates!

Work goes on making openings for the windows and doors on the south side of the barns.  Inside the barns, the internal walls are taking shape.

Window and door openings on the barn

January 2011

Thursday, June 9th, 2011

The enormous rainwater tank has been lowered into the 6 metre deep hole and pipes laid to collect all the rainwater from the roof. Sewage pipes have also been connected to the sewage treatment plant. The roof has been removed and all the rafters checked and damaged ones replaced.

November 2010

Thursday, June 9th, 2011

Work has finally started on Pitlands Barns, two months ahead of schedule. Having spent the last month emptying the barns of farm machinery, the grain dryer and lots of rubbish, the ground work started, levelling the ground, checking the foundations of the main walls and digging the footings for the internal walls. All the time excavation work was going on, George the archaeologist was checking for any Roman finds!

PIcture of foundations being dug in the stables